Technology atlas / Mineralization
Carbon mineralization
CO₂ reacts with calcium- or magnesium-rich materials such as slags or concrete to form stable carbonates.
Technical reference · Updated 2026-10-10 · No current-news claim
Where the carbon goes
Carbonate minerals are stable over geological timescales if not recalcined or acid-leached; durability is the strongest of any CCU route.
Conceptual process flow · left to right
- 01Feedstock qualification
- 02Preparation
- 03Carbonation
- 04Product testing
- 05Use
From chemistry to process
- Feedstocks
- Reactive alkaline material, CO₂
- Products
- Carbonates, Construction materials where qualified
- Catalysts
- No universal catalyst; mineral reactivity and conditioning control the process
- Conditions
- Pressure, moisture and particle size depend on feedstock and product route.
Performance & demonstrated scale
Route-specific; curing, aggregate production and waste treatment cannot share one readiness rating.
0.785 t CO₂/t CaO theoretical
Economics
Consider feedstock treatment, CO₂ delivery, product value and local transport rather than carbon uptake alone.
Climate considerations
Carbonate retention may be durable, but net removal additionally requires atmospheric carbon and a complete lifecycle balance. Calcining virgin limestone can offset carbonation uptake.
CCU Reality Check · pathway assessment
What remains to be demonstrated?
This initial assessment separates process knowledge from the evidence needed for a commercial conclusion. Missing information is left unresolved.
| Dimension | Assessment and evidence gap |
|---|---|
| CO₂ feedstock availability | No site-specific supplier, volume, purity guarantee or delivery contract has been verified. |
| Capture and delivered cost | Not quantified. Capture, conditioning, compression and transport need separate boundaries. |
| Energy and hydrogen demand | Theoretical stoichiometric or thermodynamic values are shown above. Actual process energy and feed losses remain scenario assumptions. |
| Catalyst and reactor performance | No universal catalyst; mineral reactivity and conditioning control the process. No plant lifetime or sustained performance is verified here. |
| Product separation | The process flow identifies separation stages where relevant; a quantified separation duty and cost remain unavailable. |
| CAPEX and OPEX | No plant-specific capital estimate or complete operating-cost dataset is attached. |
| Minimum selling price | Not calculated. Capital recovery, utilization, financing and a complete operating boundary are required. |
| Fossil benchmark competitiveness | No verified regional benchmark comparison. Calculator benchmark values, where shown, are illustrative. |
| Climate performance | Carbonate retention may be durable, but net removal additionally requires atmospheric carbon and a complete lifecycle balance. Calcining virgin limestone can offset carbonation uptake. |
| Scale-up bottlenecks | Reactive feedstock supply; Grinding and transport energy; Contaminants and leaching; Construction product qualification. |
| Customer and offtake readiness | No qualified-customer or executed-offtake evidence is attached to this pathway profile. |
| Policy dependence | Not assessed for a specific project or jurisdiction. Do not assume subsidies or certification eligibility. |